TecSar Engineering Inc.

Project Tracking

DescriptionBudgetActual SpentForecast% of Overall HoursActivity Code % CompleteEarned ValueRatio (Earn/ Spent)
Electrical2652626265211%20%571.591.3%
Foundations167024416556.4%19.3%322.4132.1%
Instrumentation4445425437517.1%10%446.7105.1%
Mechanical8501728653.3%18.6%15891.9%
Non-Progressible2664605.5266410.3%22.7%605.5100%
Piping2793564282410.8%17.4%487.386.4%
Post AFC32403241.2%0%0-
Process1232186.512334.7%14.6%179.996.5%
Project Support8100976.5810031.2%12.1%976.5100%
Structural101911210193.9%10.2%103.592.4%
Totals259493911.525911100%14.8%2351.398.5%

Earn Ratio by Discipline

Hours Earned By Discipline